Cleaning wind turbines in winter: how a campaign is planned when the wind is in charge

A wind farm is where the wind blows, and in winter it blows harder. That does not rule out cleaning, but it does mean planning differently. This is how a campaign is organised when the forecast writes the calendar.

Industrial drone in flight over a wind farm

Cleaning a wind turbine, whatever the method, is done with the machine stopped and without strong wind or rain. A wind farm is, by definition, where the wind blows. And in the winter months it blows harder and rains more. That does not mean you cannot clean between November and February; it means the campaign is organised differently. This is how we do it.

What a cleaning day needs

With a drone, an intervention needs wind below the equipment's operating limit during the working hours, no rain (the cleaning water is ours, not the sky's), temperature above freezing so the water does not ice on the surface, and daylight. In winter the days are short, so a useful day has fewer hours, and that counts too.

With rope access the requirements are similar and the consequences worse: a window that closes mid-morning with a technician hanging from a blade is a serious problem. With a drone, you land and wait.

How it is planned

  • Permits first. The aviation authorisation takes about 3 weeks and is requested for a period, not a day. That leaves room to choose dates within the authorised window.
  • Date confirmed the week before. With the seven-day forecast the start is set; with the 48-hour forecast it is confirmed. The site knows this from the outset and organises the machine stops with that flexibility.
  • Machines in the order the wind dictates. At a large site, the most exposed machines are left for the calmest days; the sheltered ones go first.
  • A crew that waits at the site, not in Seville. If the window is two good days in a bad week, the crew has to be there to use them. That is planned, and priced in.
  • A buffer of days. An eight-machine campaign in winter is not promised in eight days. It is promised within a window, and delivered.

What can be guaranteed and what cannot

The procedure, the crew, the permits, the price per machine and that each machine is cleaned in one day when it is cleaned: all of that can be guaranteed. The exact day cannot, with any method, and anyone who guarantees it has not spent a winter at a wind farm. The honest approach is to agree a window and an order, and to communicate every week.

Why winter is not a bad time

Because it is when many machines stop anyway for scheduled maintenance, and a stop already planned is the best moment to clean without adding lost production. And because spring campaigns fill up early: whoever plans in December for January and February has a crew; whoever calls in April for May is competing with everyone.

If you manage a site and want to make use of a scheduled winter stop, send us the number of machines, the location and the rotor diameter and within two working days we tell you which window we can cover. How a campaign is organised, step by step, is in this article.