Wind turbine cleaning: what the wind farm does before the crew arrives

A cleaning day is won or lost before the crew arrives. These are the four things the wind farm prepares, who does them, and what happens if one is missing on the day.

Eolinet technician in the field checking equipment next to a wind turbine before the job

With drone-based wind turbine cleaning, the day is won or lost before the crew drives through the site gate. A turbine that is not in the right position, a track the vehicle cannot use or an authorisation nobody has signed is not fixed by a good pilot; it is fixed by a phone call, and that call costs hours. This article sets out, for the O&M manager, what the wind farm prepares, in what order, and why it is the site and not the contractor that does it.

1. The machine stopped and in maintenance position

This comes first and constrains everything else. On the day, each turbine must be stopped with the rotor and blades set for the work: yaw turns the nacelle to face the crew and pitch puts the blades in the agreed position. Both movements are always carried out by site personnel, because they are operations on the machine's control system and we do not touch it. Both terms are in our wind energy glossary.

The useful thing is to agree the sequence beforehand: which turbines are stopped first, who puts them in position and who tells the ground crew they are ready. If a turbine cannot take the position because of an alarm or a fault, you want to know before the flight, not during it.

2. Preventive sealing of the nacelle

Before water, you close the ways it could get in. Ventilation covers, housing seams, cable glands and the joint between nacelle and tower are checked and sealed by site staff, who know each turbine model and decide what is covered and what has to keep breathing. We never go inside the nacelle. The reasoning is set out in our article on nacelle cleaning; here it is enough to say this is an eve-of-job task, not a day-of one: sealing in a hurry, with the crew waiting at the bottom, is how a seam gets forgotten.

3. Access

The ground crew carries the tank, the pump and the flying kit, and needs to reach the base of each tower by vehicle. Four things are worth confirming:

  • That the track takes the weight and size of the vehicle, including after rain.
  • That gates and barriers on site will be open, or that somebody will open them.
  • That there is somewhere to leave the vehicle without blocking other maintenance teams.
  • That the order of the turbines makes sense on the map: driving between towers is time not spent cleaning.

A tower that cannot be reached today is a turbine pushed to another day, and with a minimum of 4 turbines per campaign, every machine that drops out counts.

4. Contractor coordination

This is the least visible step and the one that delays most campaigns. Before the crew enters, the site needs the crew's details, access authorisations and each party's risk information, all exchanged before the day. It also helps to know what else is happening on site that week: if another contractor is working on a turbine, someone has to decide who does what, and in what order. We have written a whole article on this step; the point here is the calendar: it is done days ahead, not with the crew already at the gate.

What we provide

Everything else. The pilots (3 accredited), the aviation permits (in Spain, from AESA, with around 3 weeks of processing) and the civil liability insurance are on us, as is the full clean of each machine in one working day, with 0 people at height and nacelles up to 100 metres. The rest of the service is described on the wind turbine cleaning page.

A split that saves arguments

The underlying reason is the same as everywhere else in the industry: the party that knows the machine and answers for it day to day is its operator. Whatever touches the control system, the inside of the nacelle or the site calendar is the operator's call. What happens outside the housing, with the drone, is ours. When the split is clear from the start, there is nothing to argue about on the day. For the O&M provider, the cost of preparing is little more than a checklist and two phone calls.

The checklist, ready to print

  • Turbine order, and who puts each one in maintenance position.
  • Preventive nacelle sealing done, with the day before as the deadline.
  • Vehicle access confirmed to the base of every tower.
  • Contractor coordination exchanged, and a named contact on site for the day.
  • A warning to the crew if any turbine changes status before the flight.

With those five lines settled, the crew arrives, sets up and starts cleaning. Without them, losing the morning is the normal outcome. It is not about goodwill; it is about sequence: the site prepares, the contractor executes, and the two link together.